New Goochland Elementary School

Construction Project

SAVE THE DATE for the

OPEN HOUSE,

Thursday

July 18, 2024!

Ribbon-cutting ceremony starts at 4pm followed by guided tours until 7pm. Everyone is welcome!

Topping Off Ceremony 10/12/2023

(final steel beam placed on roof structure)

Construction began 1/20/2023

Logo for Goochland 2022 Bond issue

Drone footage looking from front to back of new GES

Drone footage looking at front of building with student walking track/playing field visible behind the building 3/8/2024

Drone footage of main entrance 2/2/2024

Drone image of main entrance and Bulldog Way 2/2/2024

New GES exterior taken 1/16 with snow

Snow didn't stop the work inside the building 1/6/2024

Drone footage of the new GES site 12/8/2023

Drone footage looking at the back of the school with the back parking lot ready for paving (12/8/2023)

Picture of Front Office walls/window

Administrative offices - first examples of window blocking & detailing (11/10/2023)

Drone footage of school building under construction as of 9/20/2023

Drone footage of building with only steel columns in sector C (9/22/2023)

Rainbow over the job site

Pretty sunrise rainbow over the job site - but no rain delays for the project yet

Curb and gutter laid down near main parking lot. Shows machine.

Machine lays down first concrete curb and gutter near main parking lot 7/18/2023

Large crane and crew lay concrete flooring in New GES cafeteria on 6/30/2023

Concrete pad poured in cafeteria area during early morning of 6/30/2023

Gym walls with structural steel column rising to second story

Placement of CMU blocks around steel column for gym high walls, sector A (view – southeast, 5/19)

Construction workers building concrete block wall for gym

Gym walls starting to rise (4/19/2023)

Drone image of new GES construction site with graded school pad clearly visible

Drone image of cleared and graded building pad (looking southeast, 3/24/2023)

Image of land cleared for future building pad

Land cleared and graded for building pad

Picture of bulldozer creating a road

Entrance being cut off Bulldog Way

Latest update:

3/20/2024 Large number of skilled workers inside the building. See the difference of two weeks overlooking the future library area: 2/29/2024 time lapse and 3/12/2024 time lapse

2/13/2024 School Board presentation by MBP Project Manager Ryan Waldrop.

2/5/2024 Permanent water to the building. Walls and interior windows continue to go up as seen in the newest time lapse of the future "gifted" classroom (1/18/2024).

1/19/2024 As cold weather has set in, a large number of subcontractors are working on walls and other components inside the building. View the time lapse video of interior construction over the learning stairs in the academic wing (through 1/11/2024).

12/8/2023 Dominion Energy electrifies the site, parts of the building become enclosed with window panes, plastic and sheathing so that the building can be heated and inside work intensifies.

11/10/2023 Admin section has HVAC duct work, fireproofing, window blocking in place with the brick exterior started on the north side (gym wall). Section B now has exterior wallboard sheathing completed and Section C has exterior metal framing completed. See time lapse movie through 10/24/2023.

10/10/2023 Steel infrastructure completed and 2nd floor concrete floors poured in section B. Steel infrastructure in section C almost complete. Walls going up in section A (admin suite). Utilities extended to site and road widening on Bulldog Way continues. See time lapse movie through 10/3/2023.

8/15/2023 Concrete ground floors complete. Steel infrastructure rising to second level in section B. Off-site work near the high school completed for the start of the school year. Continuing roadwork and flagging as lanes widened on Bulldog Way. See time lapse movie through 8/10/2023.

7/22/2023 Concrete ground floor pours have extended to section B (middle of school). Steel infrastructure and roof sheeting has been placed on section A (gym, admin & cafeteria). See time lapse movie through 7/6/2023.

6/30/2023 The first concrete pour occurred for base flooring in the cafeteria and admin wing sections. The gym and elevator CMU walls are finished and utility extension and road widening work has started on Bulldog Way. See time lapse movie through 6/28.

5/19/2023 Foundation walls and footings in all three sections completed. On-site water lines laid alongside almost completed sewer and stormwater piping. See time lapse movie through 5/8.

4/28/2023 Structural steel columns raised on gym wall. Continue footings, CMU walls, waterproofing and underground plumbing & electrical - admin area and first half of classroom wing. See time lapse movie through 5/1.

4/21/2023 Work continues on the building pad - footings and underground electrical and plumbing conduits. Concrete walls are going up for the gym. See time lapse movie.

4/7/2023 Topsoil mountain is starting to be sifted and placed in graded areas. Footings pored on admin/cafeteria/gym section of the school. Stormwater system 75% complete. Manholes and large sewer pipes installed. (See drone footage and time lapse movie.)

3/24/2023 Grading continues with the building pad created for footings soon to be pored. Sewer and stormwater pipe being installed on east edge. Construction trailers installed in future bus loop (west edge).

3/7/2023 Timbering complete. Grading of cleared areas proceeding in earnest with sewer lines being installed on site. (see Slide deck)

2/10/2023 Entrance 1 & 2 complete. Silt fences around perimeter complete. Timbering of all impacted areas will proceed when sediment basins are finished.

1/20/2023 First heavy equipment now on site and the main construction entrance is being cut through woods off Bulldog Way.

1/11/2023 - Dr. Raley signed the Shockey construction contract and Notice to Proceed was granted for 1/12/2023. The afternoon kick-off meeting was attended by representatives from GCPS staff and School Board, Stantec, MBP, Shockey and Goochland County.

Significant events - contract signing 1/11/2023, groundbreaking ceremony 2/9/2023; construction trailers installed 3/24/2023; GCPS staff and board member tour of project 4/14/2023

Draft rendering of new GES from main entrance from bus loop

Possible view of new GES main entrance from bus loop

Draft rendering of new GES front office reception area

Possible view of new GES reception area with transaction window

Draft rendering of new GES cafeteria, view from main entrance

Possible view of new GES cafeteria, view from main entrance

Draft rendering of new GES open library, view from classroom hallway on second floor

Possible view of new GES open library from 2nd floor classroom hallway

Project Timeline (revised 5/2022)

Design Timeline

Construction Timeline

Additional Resources

Sign on new GES site on Bulldog Way

Project design update - Stantec Presentation 5/10/2022

Second Schematic Design - Stantec Presentation 3/29/2022

Project Update and Alternative Options Considered, Dr. Raley presentation to Joint Boards, March 8, 2022.

First Schematic Design - Stantec Presentation 12/14/2021

Images from the GES Design Charette on October 28, 2021:

Images from the GES Design Community Meeting on October 18, 2021:

September 13, 2021 Community Pre-design Presentation (PDF, Stantec)

Images from the Steering Committee's new school tours on September 8, 2021: